TC52

Add Support Beams to Rear Access Dock

Task Card Description

1

Make sure every floorboard is clearly marked in order (1-2-3-4, etc.) before removing anything.

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

2

Remove all floorboards and set them aside carefully. Confirm that all long beams are fully exposed.

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

3

Temporarily screw the existing beams together so their alignment stays the same once bolts are removed.

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

4

Remove the bolts from the beams but keep all washers, as we need them.

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

5

Position the 3 new beams so each existing beam gets paired�creating a 3-beam stack at each location.Bolt the beams together to hold them in place in correct alignment. (Martin do this)

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

6

Use the existing hole that goes through the two original beams as a drill guide. Run the drill bit through that hole to open the path through the new third beam. Repeat for each hole

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

7

Cut the left over wood from transversal beams (let Martin do this)

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

8

using new screws re position the floor boards covering the beams.

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png

TC52

9

paint the dock green

ChatGPT Image Oct 16, 2025, 03_27_17 PM.png